Trypilska Thermal Power Plant

Трипільська теплова електростанція

Energy and Power energy.tpp Assessed Rebuildable

Location

OblastKyiv
RaionObukhiv
SettlementUkrainka
AddressTrypilska TPP, Ukrainka, Obukhiv Raion, Kyiv Oblast
Coordinates50.1073°N, 30.7636°E

View on OpenStreetMap ↗

Damage Record

Incident date2024-04-11
Incident typemissile strike
Destruction levelDestroyed (95–110%)
Re-damage count0
Verified byKSE, PRESS, UA_GOV, UN_OCHA

Evidence sources

Wartime Status

Lifecycle stageAssessed
RebuildabilityRebuildable
Sovereign risk bandelevated
De-risking instrumentsMIGA War & Civil Disturbance Insurance; EBRD Risk Sharing Facility; EU Facility First-Loss Guarantee

Physical Specifications

installed capacity mw 1,800 MW extracted from source
site area ha 165 ha extracted from source
construction year 1,969 year extracted from source

Reconstruction Cost Estimates

Cost figures are estimates derived from published unit-cost benchmarks (RDNA4, KSE Institute) and named comparable Ukrainian precedents. Not guarantees, not procurement quotes. All amounts in USD millions.

Baseline

Repair to pre-war condition

USD 1,045.2M – USD 2,676.6M
Central: USD 1,860.9M

Code-compliant

Rebuild to current EU/UA building codes

USD 1,201.9M – USD 3,345.4M
Central: USD 2,273.7M

Build-back-better

Rebuild with technology overlays

USD 1,358.6M – USD 4,281.5M
Central: USD 2,820.7M
Technology overlays: combined cycle gascarbon capture readysmart grid integrationgrid scale storagehydrogen readiness

Financing Structures

Twelve-tranche capital stack derived from sector × path templates (RDNA4, EU Facility, EBRD). All tranches sum to 100%.

Baseline

10%5%5%25%25%5%15%10%
Show full capital stack
Tranche%
Grant (Pillar I)10%
ERA / Frozen Assets5%
First-loss / Guarantee5%
Concessional IFI Debt25%
Senior IFI (near-mkt)25%
ECA-Covered Debt—
DFI Equity / Quasi-eq.5%
Public / Municipal Eq.15%
Diaspora / Patriotic Bd—
Commercial Bank Debt10%
Institutional Debt—
Private Equity / Infra—

Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export

ENERGY_BASELINE

Code-compliant

20%5%5%25%20%5%15%5%
Show full capital stack
Tranche%
Grant (Pillar I)20%
ERA / Frozen Assets5%
First-loss / Guarantee5%
Concessional IFI Debt25%
Senior IFI (near-mkt)20%
ECA-Covered Debt—
DFI Equity / Quasi-eq.5%
Public / Municipal Eq.15%
Diaspora / Patriotic Bd—
Commercial Bank Debt5%
Institutional Debt—
Private Equity / Infra—

Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export

ENERGY_CODE_COMPLIANT

Build-back-better

30%5%5%25%15%5%10%5%

Large thermal power reconstruction with build-back-better pivot to combined-cycle gas (lower emissions vs. current coal-fired base). EU Facility energy-security track eligible; EBRD Energy Efficiency and Resilience Facility applicable. Private co-investment (DTEK equity) credible given operator's existing portfolio. EU green conditionality requires carbon-transition roadmap — combined-cycle pathway meets this threshold. Note: coal plant baseline rebuild unlikely to receive EU grant support; code-compliant and BBB paths assume fuel-switch to gas or hybrid.

Show full capital stack
Tranche%
Grant (Pillar I)30%
ERA / Frozen Assets5%
First-loss / Guarantee5%
Concessional IFI Debt25%
Senior IFI (near-mkt)15%
ECA-Covered Debt—
DFI Equity / Quasi-eq.5%
Public / Municipal Eq.10%
Diaspora / Patriotic Bd—
Commercial Bank Debt5%
Institutional Debt—
Private Equity / Infra—

Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export

ENERGY_BBB

Record Metadata

Asset IDTRYPILSKA_TPP_2024_04_11
Last reviewed2026-10-22
Schema version1.0.0
Tagsenergy, thermal_power, dtek, kyiv_oblast, missile_strike, large_scale, grid_critical