Trypilska Thermal Power Plant
Трипільська теплова електростанція
Location
| Oblast | Kyiv |
|---|---|
| Raion | Obukhiv |
| Settlement | Ukrainka |
| Address | Trypilska TPP, Ukrainka, Obukhiv Raion, Kyiv Oblast |
| Coordinates | 50.1073°N, 30.7636°E |
Damage Record
| Incident date | 2024-04-11 |
|---|---|
| Incident type | missile strike |
| Destruction level | Destroyed (95–110%) |
| Re-damage count | 0 |
| Verified by | KSE, PRESS, UA_GOV, UN_OCHA |
Evidence sources
Wartime Status
| Lifecycle stage | Assessed |
|---|---|
| Rebuildability | Rebuildable |
| Sovereign risk band | elevated |
| De-risking instruments | MIGA War & Civil Disturbance Insurance; EBRD Risk Sharing Facility; EU Facility First-Loss Guarantee |
Physical Specifications
| installed capacity mw | 1,800 MW extracted from source |
|---|---|
| site area ha | 165 ha extracted from source |
| construction year | 1,969 year extracted from source |
Reconstruction Cost Estimates
Cost figures are estimates derived from published unit-cost benchmarks (RDNA4, KSE Institute) and named comparable Ukrainian precedents. Not guarantees, not procurement quotes. All amounts in USD millions.
Baseline
Repair to pre-war condition
Code-compliant
Rebuild to current EU/UA building codes
Build-back-better
Rebuild with technology overlays
Financing Structures
Twelve-tranche capital stack derived from sector × path templates (RDNA4, EU Facility, EBRD). All tranches sum to 100%.
Baseline
Show full capital stack
| Tranche | % |
|---|---|
| Grant (Pillar I) | 10% |
| ERA / Frozen Assets | 5% |
| First-loss / Guarantee | 5% |
| Concessional IFI Debt | 25% |
| Senior IFI (near-mkt) | 25% |
| ECA-Covered Debt | — |
| DFI Equity / Quasi-eq. | 5% |
| Public / Municipal Eq. | 15% |
| Diaspora / Patriotic Bd | — |
| Commercial Bank Debt | 10% |
| Institutional Debt | — |
| Private Equity / Infra | — |
Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export
ENERGY_BASELINE
Code-compliant
Show full capital stack
| Tranche | % |
|---|---|
| Grant (Pillar I) | 20% |
| ERA / Frozen Assets | 5% |
| First-loss / Guarantee | 5% |
| Concessional IFI Debt | 25% |
| Senior IFI (near-mkt) | 20% |
| ECA-Covered Debt | — |
| DFI Equity / Quasi-eq. | 5% |
| Public / Municipal Eq. | 15% |
| Diaspora / Patriotic Bd | — |
| Commercial Bank Debt | 5% |
| Institutional Debt | — |
| Private Equity / Infra | — |
Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export
ENERGY_CODE_COMPLIANT
Build-back-better
Large thermal power reconstruction with build-back-better pivot to combined-cycle gas (lower emissions vs. current coal-fired base). EU Facility energy-security track eligible; EBRD Energy Efficiency and Resilience Facility applicable. Private co-investment (DTEK equity) credible given operator's existing portfolio. EU green conditionality requires carbon-transition roadmap — combined-cycle pathway meets this threshold. Note: coal plant baseline rebuild unlikely to receive EU grant support; code-compliant and BBB paths assume fuel-switch to gas or hybrid.
Show full capital stack
| Tranche | % |
|---|---|
| Grant (Pillar I) | 30% |
| ERA / Frozen Assets | 5% |
| First-loss / Guarantee | 5% |
| Concessional IFI Debt | 25% |
| Senior IFI (near-mkt) | 15% |
| ECA-Covered Debt | — |
| DFI Equity / Quasi-eq. | 5% |
| Public / Municipal Eq. | 10% |
| Diaspora / Patriotic Bd | — |
| Commercial Bank Debt | 5% |
| Institutional Debt | — |
| Private Equity / Infra | — |
Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export
ENERGY_BBB
Record Metadata
| Asset ID | TRYPILSKA_TPP_2024_04_11 |
|---|---|
| Last reviewed | 2026-10-22 |
| Schema version | 1.0.0 |
| Tags | energy, thermal_power, dtek, kyiv_oblast, missile_strike, large_scale, grid_critical |