Zmiivska Thermal Power Plant

Змієвська теплова електростанція

⚠ Re-damaged 2 time(s) — material investor-information field
Energy and Power energy.tpp Assessed Rebuildable

Location

OblastKharkiv
RaionZmiyiv
SettlementZmiiv
AddressZmiivska TPP, Zmiiv, Kharkiv Oblast
Coordinates49.6600°N, 36.3800°E

View on OpenStreetMap ↗

Damage Record

Incident date2024-03-22
Incident typemissile strike
Destruction levelDestroyed (95–110%)
Re-damage count2 ⚠ Material investor-information field
Verified byKSE, PRESS, UA_GOV, UN_OCHA

Evidence sources

Wartime Status

Lifecycle stageAssessed
RebuildabilityRebuildable
Sovereign risk bandelevated
De-risking instrumentsMIGA War & Civil Disturbance Insurance; EBRD Risk Sharing Facility; EU Facility First-Loss Guarantee

Physical Specifications

installed capacity mw 2,400 MW extracted from source

Reconstruction Cost Estimates

Cost figures are estimates derived from published unit-cost benchmarks (RDNA4, KSE Institute) and named comparable Ukrainian precedents. Not guarantees, not procurement quotes. All amounts in USD millions.

Baseline

Repair to pre-war condition

USD 1,687.4M – USD 4,417.2M
Central: USD 3,053M

Code-compliant

Rebuild to current EU/UA building codes

USD 1,940.7M – USD 5,522.6M
Central: USD 3,731.6M

Build-back-better

Rebuild with technology overlays

USD 2,193.9M – USD 7,068.6M
Central: USD 4,631.3M

Financing Structures

Twelve-tranche capital stack derived from sector × path templates (RDNA4, EU Facility, EBRD). All tranches sum to 100%.

Baseline

10%5%5%25%25%5%15%10%
Show full capital stack
Tranche%
Grant (Pillar I)10%
ERA / Frozen Assets5%
First-loss / Guarantee5%
Concessional IFI Debt25%
Senior IFI (near-mkt)25%
ECA-Covered Debt—
DFI Equity / Quasi-eq.5%
Public / Municipal Eq.15%
Diaspora / Patriotic Bd—
Commercial Bank Debt10%
Institutional Debt—
Private Equity / Infra—

Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export

ENERGY_BASELINE

Code-compliant

20%5%5%25%20%5%15%5%
Show full capital stack
Tranche%
Grant (Pillar I)20%
ERA / Frozen Assets5%
First-loss / Guarantee5%
Concessional IFI Debt25%
Senior IFI (near-mkt)20%
ECA-Covered Debt—
DFI Equity / Quasi-eq.5%
Public / Municipal Eq.15%
Diaspora / Patriotic Bd—
Commercial Bank Debt5%
Institutional Debt—
Private Equity / Infra—

Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export

ENERGY_CODE_COMPLIANT

Build-back-better

30%5%5%25%15%5%10%5%

EU Facility energy-security track; EBRD Energy Efficiency and Resilience Facility; private co-investment (operator equity) credible for BBB path with carbon-transition roadmap

Show full capital stack
Tranche%
Grant (Pillar I)30%
ERA / Frozen Assets5%
First-loss / Guarantee5%
Concessional IFI Debt25%
Senior IFI (near-mkt)15%
ECA-Covered Debt—
DFI Equity / Quasi-eq.5%
Public / Municipal Eq.10%
Diaspora / Patriotic Bd—
Commercial Bank Debt5%
Institutional Debt—
Private Equity / Infra—

Political risk insurance (required): MIGA War & Civil Disturbance, UK Export Finance, BPIFrance Assurance Export

ENERGY_BBB

Record Metadata

Asset IDZMIIVSKA_TPP_2024_03_22
Last reviewed2026-10-22
Schema version1.0.0
Tagsenergy, thermal_power, centrenergo, kharkiv_oblast, missile_strike, large_scale, re_damaged, grid_critical